Iligan Coastal Road and Esplanade Project Update as of June 2020

Watch the latest update of the Iligan Coastal Road and Esplanade project as of June 2020.

In 2017, Congressman Freddie Siao lobbied for multi-million infrastructure projects for the city of Iligan. Congress approved these priority projects for the development of Iligan.

  1. The Iligan City Coastal Bypass Road (from Sta. Filomena to Buru-un)
  2. The Iligan-Cagayan de Oro Alternate Road
  3. Iligan Esplanade (along Mandulog River)
  4. Iligan Hinterland Roads (from C-3 to Mandulog, Dulag and Digkilaan)

Implemented by the Department of Public Works and Highways (DPWH).

The construction of Iligan Esplande Phase 1 (2019) started on June 20, 2019 with a project cost of PHP 72,375,000.00. The Iligan Esplande Phase 2 (2020) started on February 21, 2020 with a project cost of PHP 46,575,568.12.

The construction of Iligan Coastal Bypass Road Phase 1 started on February 20, 2018 with a project cost of PHP 73.7 million. The Iligan Bypass Road Phase 2 started on March 19, 2018 with a project cost of PHP 45.4 million.

The bypass and alternate roads aim to decongest the city allowing vehicle traffic to go faster.

Video courtesy of Congressman Freddie Siao.

WHAT'S NEW