VIDEO: 45.5 Million CDO-Airport-Bukidnon Road Slope Protection Project August 2018 Progress Update

Watch the latest progress of the 45.5 million CDO-Airport-Bukidnon Road slope protection project as of August 2018. The slip, slope, collapse and landslide protection secondary road project is set for completion on October 15, 2018.

The PHP 45,521,299.41 road project near Pryce Plaza in Cagayan de Oro started on April 19, 2018, and expected to be completed in 179 calendar days.

Here are the latest aerial photos of the CDO-Airport-Bukidnon road slop protection project progress as of August 2018: https://www.projectlupad.com/45-5-million-cdo-airport-bukidnon-road-project-near-pryce-plaza-as-of-august-2018/

WHAT'S NEW